Restart international commissioning

We are excited that our service team can slowly restart international commissioning! For a natural gas transmission system operator in Greece, we are revamping a metering control system for Kipi border station, a large gas metering station at the border of Greece and Turkey.

Commissioning project details:

  • Our team was COVID-19 tested prior to site mobilization and is working according to strict guidelines;
  • This revamp, performed on live flowing stations, includes replacement of obsolete Elster-Instromet FC2000 flow computers for their natural successors, Ex-i SFC3000 flow computers;
  • The existing and obsoleted HMI package is upgraded to the latest version of ISSplus software;
  • The complete existing Schneider Modicon Quantum PLC is replaced by a Schneider M580 including replacement of all the I/O racks.

Our team is well on schedule to meet the targeted handover date of 12 September.